Downtown Electric Project Update – November 2025

Friday, November 07, 2025

Main News Photo

Downtown Electric Project Update – November 2025

The City of Falls City continues to make progress on the Downtown Underground Electric Project, which is improving the reliability, safety, and appearance of our downtown electric system.

Cutovers Have Begun

The process of transferring customers’ electric service from existing overhead lines to the newly installed underground system is now underway. Watts Electric will contact each affected customer directly to schedule a temporary outage — generally lasting 1 to 5 hours — to complete the transfer. Once your service is moved underground, the overhead connection will be removed.

Spectrum Services

Spectrum will coordinate its own cable transfers separately. These will not be handled by Watts Electric.

Project Phases and Schedule

PhaseAreaCutover Schedule
1Chase/Stone – 11th to 16thOct 27–Nov 14
2Chase/Stone – 16th to 20thNov 17–Dec 5
3Stone/Harlan – 11th to 16thTBD
4Stone/Harlan – 16th to 18thTBD

After Phases 1 and 2 are complete, removal of the overhead poles and wires is expected to begin as early as January 2026, weather permitting. The full undergrounding project is anticipated to be completed by Spring 2026.

Additional Resources

Contact

For questions or concerns, please contact the Falls City Utility Office at 402-245-2851.

Category: News, Utilities