Construction continues for the Natural Gas Improvement Project
Friday, May 30, 2025

Construction is underway for the multi-phase Natural Gas Improvement Project. Each year sections of town are selected based upon existing infrastructure conditions and utility easement accessibility. This year, Falls City is upgrading the natural gas infrastructure in the area highlighted on the map! Work is underway and expected to take about 90 days, with crews moving west to east at roughly one block per week.
✅ New gas mains and service lines
✅ Valve installation, tie-ins, purging and abandonment
✅ Surface restoration and cleanup included
Thank you for your patience as we work to improve safety and reliability in your neighborhood!
Questions? Contact Marc Ramsey, Natural Gas Utility Superintendent: 402-245-2851